660 MW Thar Coal Power Project, part of the Early Harvest Projects of CPEC, achieves commercial operations

  • July 10, 2019
660 MW Thar Coal Power Project, part of the Early Harvest Projects of CPEC, achieves commercial operations
Image caption 660 MW Thar Coal Power Project, part of the Early Harvest Projects of CPEC, achieves commercial operations

ISLAMABAD: The Engro Powergen Thar (Pvt) Limited (EPTL) involved in extensive testing of 660MW coal-based power plant and coal mining project in Thar on Tuesday declared to have successfully completed all relevant inspections and commissioning of the power plant, thereby achieving commercial operations date (COD).

“The COD milestone of both the mining and the power projects is a significant achi­eve­ment given that the Thar dream has been an elusive reality for millions of Pakistanis for over 27 years,” claimed an EPTL statement.

The EPTL is a majority-owned company of Engro Energy and Sindh Engro Coal Mining Company (SECMC), which itself is a joint venture of Engro Energy and the Sindh government.

Developed in a record time and as per schedule and within projected costs, the Thar coal project is part of the early harvest component of the China Pakistan Economic Corridor (CPEC)) framework.

SECMC plans to double production capacity of coal mine to 7.6 million tonnes per annum by 2021

The coal mining and power plant project began in 2016 after the financial close of the project led by Engro Energy in collaboration with other commercial partners, including the Sindh government, Thal Limited, HBL, Hubco, State Power Investment Corporation (SPIC) of China and the China Machinery Engineering Corporation (CMEC) for the mine project.

The SECMC had unearthed the first layer of coal in June 2018 and completed the 60-day testing period of steady state production of on-specification coal. This culminated the first phase of the mining project. The EPTL completed work on the construction of two 330-MW mine-mouth power plants and synchronised them with the nat­ional grid by April 2019. The company has since been involved in extensive testing of both the power units and has successfully completed all relevant inspections and commissioning of the plant thereby achieving the COD.

On the occasion, EPTL chief executive officer Ahsan Zafar Syed said the company completed extensive testing of the systems to ensure quality of power supply without compromising the safety of the project.

SECMC CEO Syed Abul Fazal Rizvi said the first phase of the mining project was completed ahead of schedule, well within the projected costs and with a stellar safety record. “We are now working diligently to pursue second phase of the mining activity as per our expansion plans where we intend to economise the mine and double the production capacity to 7.6 million tonnes per annum (MPTA) for the additional 2x330MW power plant scheduled to come online in 2021,” he said.

Ghias Khan, president of Engro Corporation, termed the COD of Thar coal mine and the power plant monumental and said it showcased not just the company’s ability to deliver on mega projects but also underscored the success of public-private partnership models to deploy inclusive development in the country.

Archives

Cabinet committee meeting on CPEC decided to prese nt the CPEC Authority's draft act before the federal cabinet for approval.
Prime Minister Khan Closely Monitors Progress on Development of SEZs
CPEC and Scientific Collaboration, COMSATS Hosts Guangzhou University Delegation
China: Attractive Market for Pakistani Kinnow Export, Secretary-General BMP
CPEC's Regional Connectivity Plan via Railway Proposed
1320 MW HUBCO Power Plant under CPEC Successfully Begins Commercial Operation
Multan-Sukkur Motorway to Urbanize Under-Developed Regions
Custom Collects China's Recent Present to Pakistan: Three Cargo Scanners
Package of Growth, Hope and Development Underlined for Balochistan under CPEC in NDC Meeting
NDC to Approve Gwadar Master Plan in its First Session
China earmarks $1 billion grant for various socio-economic projects in Pakistan
Three motorway projects completed under CPEC to open for general public by the end of August
Koreans willing to invest in CPEC
Pakistan and China share an identical world view: Gen Zubair
Pakistani Women to Rejuvenate Chinese Handicraft Industry
Pakistan to learn from the Chinese experience, ensures full support to investors: Chairman BOI
Pakistan and China to cooperate within the taxation domain
Government green signals the $8.2 billion ML-1 project
CPEC authority to get a full shape prior to JCC meeting
CPEC to boost economic growth in Balochistan
Phase II of CPEC to be a catalyst for industrial and agricultural development
Chinese firm Timesaco vows to overhaul the service sector in Pakistan by investing 20 million USD
China keen to enhance cooperation and connectivity through CPEC
Chinese Delegation receives flowers from the students of SBK Womens University Quetta
CPEC will reinvigorate Pakistan's economic conditions: Cheng Xizhong
Formation of CPEC authority is a proof of Pakistan's trust in CPEC
Transportation infrastructure overhauled after the completion of Sukkur-Multan Motorway
Speaker National Assembly Asad Qaiser terms China Pakistan relations a symbiosis Speaker National Assembly Asad Qaiser terms China Pakistan relations a symbiosis
CPEC to initiate an era of success for Balochistan
Quetta Declaration unanimously adopted by all major Balochistan political parties and civil society